Primary Purpose of the Critical Path Method

< Prev
Next >
Which of the following best describes the primary purpose of the critical path method (CPM)?
AIt lists issues that have developed during a project.
BIt identifies resources that are critical to project completion.
CIt identifies activities that, if delayed, could delay the entire project.
DIt provides time estimates for the completion of all project activities.